Planning Phases
Phase |
Details |
Actions | Timelines |
• Award of Project • Existing Core Plan and Policy Analysis • Define Scope, Work Plan & Budget • Planning Process Development + Finalization |
• Consultant Start-up Workshop • Implement Campus Plan Website + Social Media |
June, 2011 | |
• Identify Issues and Ideas • Built Form & Campus Legacy Review • Campus Precincts & Districts Review • Access, Movement & Parking Analysis • Review Student Housing Demand Forecasts |
• Implement Campus Plan Website + Social Media Site | July to Dec, 2011 | |
• Comparative Campus Planning Study • Vision & Outcome Statement |
• Open House I – Community Outreach • Focus Groups • Campus Plan Website - Online Feedback Form |
Jan, 2012 |
Reporting
Mid-way through this 12 month process, Campus Planning & Architecture and the planning team of Moriyama + Teshima Architects & Planners through their sub-consultant Educational Consulting Services will provide a summary report evolving from the initial stages of investigative work.
The values that will be articulated in this Master Plan Directions Report (ECS), entitled "A Time of Transition, a Time of Possibilities," will provide a foundation for our consultants to develop key Master Plan Directions and Objectives that will in turn form the basis for developing the conceptual plans.
Phase |
Details | Actions | Timelines |
• Sustainable Campus Visioning and Priorities • Public Realm Improvement Plan • Campus Gateway Study • Analysis of Key Directions |
• Contextual basis of planning to be presented to leadership team. Iterative master plan alternatives to be developed by consulting team and CP+A. Development process to be available on the UCMP website as it evolves. • Senior leadership review of (3) distinct Conceptual Plans and evaluation of each. • Senior leadership review of (2) distinct Conceptual Plans with first public Open House for general comment from the campus community (Community Outreach - May 1, 2012). • Campus Plan Website - Online Feedback Form available for general comment. |
January thru June, 2012 | |
• Draft Campus Master Plan • Presentation of Draft Plan to Board of Governors. |
• Two (2) Conceptual Alternatives are developed into a singular Draft Campus Master Plan. • Complete and Submit Draft Campus Plan to Facilities for review, minor edits and recommendation to senior administration (July - August). • Draft Campus Master Plan provided online. • Campus Plan Website - Online Feedback Form available for general comment. |
July to December, 2012 | |
• Final University Campus Master Plan to Board of Governors for adoption. |
• Adoption of the finalized Campus Master Plan subject to Campus Planning & Architecture (UoL Facilities), University Campus Plan Steering Committee and University Board approval. • Public Open House and release of final UCMP document to the campus community. |
January, 2013 |